In Germany, construction works take place throughout the year, particularly at weekends or during off-peak hours, which may result in train cancellations, diversions or delays. In the online timetable, these measures affecting rail traffic are sometimes only visible at short notice.
7 February 2026 to 31 October 2026: Timetable changes for EC Zurich–Munich.
From 7 February to 31 October 2026, timetable changes will affect the Munich–Buchloe section of the Zurich–Munich route. The reason: on some sections in Germany, line speed will need to be reduced for several kilometres.
In EuroCity traffic between Zurich and Munich, travel times are extended by around 10 minutes. In traffic from Munich to Zurich, some EuroCity trains depart from Munich towards Zurich a few minutes earlier. This adjustment has no impact on connections within Switzerland.
1 May to 10 July 2026: Construction work between Hanover and Hamburg.
From 1 May to 10 July 2026, construction work will take place between Hanover and Hamburg. Trains will be diverted on this route, resulting in an increase in journey time of approximately 30 minutes.
10 July 2026 to 22 July 2026: Construction works between Zurich HB and Munich.
From 10.07.2026 to 22.07.2026, construction works will take place on various sections between Lindau-Reutin and München Hauptbahnhof. From 11.07.2026 to 12.07.2026 and from 17.07.2026 to 20.07.2026, all EC trains will be cancelled between Lindau-Reutin and Munich. On the remaining days, only selected lines will be affected by cancellations between Lindau-Reutin and Munich. For most cancelled EC connections, replacement buses will operate between Lindau-Reutin and München ZOB Hackerbrücke.
3 August 2026 to 16 August 2026: construction work between Freiburg im Breisgau and Offenburg.
From 3 August to 16 August 2026, construction work will take place between Freiburg im Breisgau and Offenburg. From 3 August to 7 August and from 10 August to 14 August 2026, individual ICE services towards Germany from Basel SBB and in the opposite direction will be cancelled.
From 8 August to 9 August and from 15 August to 16 August, all ICE services towards Germany from Basel SBB and in the opposite direction will be cancelled. An ICE will run hourly between Basel SBB and Freiburg im Breisgau in both directions. Replacement buses will operate between Freiburg im Breisgau and Offenburg. Journey times will be extended by up to 60 minutes. Some trains will run throughout, but will be diverted between Zurich HB and Offenburg and will not stop at all stations.
The night trains from Zurich HB to Prague, Berlin, Hamburg-Altona and Amsterdam C., as well as in the opposite direction, will be diverted on the nights of 7/8 August, 8/9 August, 9/10 August, 14/15 August, 15/16 August and 16/17 August and will not stop at all stations.
13 August 2026 to 24 August 2026: Construction works between Zurich HB and Munich.
From 13.08.2026 to 24.08.2026, construction work will take place between Leutkirch and Kisslegg on the Zurich HB–Munich route. From 15.08.2026 to 21.08.2026, all EC trains will be cancelled from Lindau-Reutin. On 13.08.2026, 14.08.2026, 22.08.2026 and 24.08.2026, only individual EC trains between Lindau-Reutin and Munich will be cancelled. Replacement buses will operate between Lindau-Reutin and München ZOB Hackerbrücke for most of the cancelled EC services.
25 August 2026 to 5 September 2026: construction work between Zurich HB and Munich.
From 25 August 2026 to 5 September 2026, construction work will take place between Buchloe and Munich on the Zurich HB–Munich route. On 25 August 2026 and 5 September 2026, individual EC services will be cancelled. From 26 August 2026 to 4 September 2026, all EC services between Lindau-Reutin and Munich will be cancelled. For most of the cancelled EC services, replacement buses will operate between Lindau-Reutin and Munich ZOB Hackerbrücke.